Media Mennonite Church
Media Mennonite Church

The Work at Waterway

April 16, 2019

A few highlights from the Work at Waterway this week

  1. The unfortunately-placed telephone pole in the middle of our new driveway will be moved soon. We're thankful that this process is moving more quickly than it could be.
  2. Two loads of structural steel and metal roofing arrive today from Tulsa,OK. Another load is expected later this week. Very cool stuff.
  3. Trenches are being dug for utilities and for concrete footers. It is looking like some concrete footers will be poured later this week.
  4. Some of the bigger excavating equipment is actually leaving the site due to the fact that some of the biggest earth moving is done for awhile. We'll likely see more building progress and not just dirt moving in the next few weeks.

Above, this 53-foot trailer from Tulsa, Oklahoma carried metal roofing material, metal posts for interior walls and metal edging for our roof.

Kenny Gilbert is the Nowland worker on that same 53-foot trailer directing the unloading.

Here is where the footer will be poured for our "back wall" - the wall of the church building facing south. Our nursery will be here on the left, where the green rods are sitting in the dirt. Then a classroom, the kitchen and our back door. the sanctuary and pulpit will be on the left at the far end of this trench.

March 29, 2019

And here is this week’s construction connection...

Below you can see the same picture twice - once as it was on March 17, once with markups showing approximate location of driveway, parking and building. Thanks Ross Johnson for the drone photos!

For those of you who really like to nerd out on excavation, here is one of the three “dry wells” that will be under our parking lots and yards to help storm water soak in rather than run off. The excavator at the edge and the swimming pool in the neighbors’ yard give you some perspective on how big each of these dry wells is.

And this is why we do all of this. This is the view looking north into Oxford from directly above our new building. Every person in every bedroom in every house needs the Lord - and maybe God will use us to help introduce some of these neighbors to Jesus. Pick out a house and pray for the family there.

 

February 7, 2019

 

If you've been past our Waterway Property, you've noticed a lot of activity in the past few weeks. Initially, Andrews Excavators delivered some equipment, cut in the constrution entrance (which will eventually be our main driveway) and delivered materials. Our  main driveway will be directly across the road from Redbud Drive, as required by East Nottingh Township, but the old driveway will serve the Oaks House until the new drive and parking lots are completed.

CONSTRUCTION ENTRANCE/FUTURE DRIVEWAY VIEWED FROM WATERWAY ROAD

The excavation project is really ramping up. Last Wednesday and Thursday (January 30-31) when is was 10-15 degrees during the day, workers from Andrews Excavation were busy moving topsoil and installing pipes and manholes for the huge drainage fields that allow for stormwater management. Mike and Carl were working hard to help us get our work done, even in the snow.

SETTING A JUNCTION BOX, WITH WATER PIPE IN THE BACKGROUND

THERE WERE A FEW DAYS WHEN IT WASN'T MUDDY OR SNOWY. THIS PHOTO WAS TAKEN JANUARY 29, RIGHT BEFORE THE SNOW.

The excavation peice of our project is huge. Everything about this process has been gone over with a fine-toothed comb by township, county and state offices. No one wants water runoff to be a problem, so we've got an extensive network of drainage systems under our parking lots and open spaces. This is why  most of the topsoil around the project will be stripped away and set aside in large piles, then infrastructure will be installed, and then at the end of the project much of that topsoil will be replaced. A lot of dirt will be moved around in the next few months.

ORANGE FENCES SURROUND DRYWELL AREAS THAT WILL BE DRAIN FIELDS

Some of the most dramatic process so far was the removal of many of the old maple trees around the driveway and house. John Santana from R&H Excavation helped remove these trees February 6-7. He reported that he hoped to take a few logs home to salvage some boards, but from all the trees he took down, only 4 small logs were solid and sturdy enough to be used, so he didn't even bother keeping those.  Many of our trees were hollow and in rough shape. The tree-lined driveway will be missed, but we've got an extensive landscape plan (mandated and inspected by our township) that will be in place when our project is completed, including new trees along our new driveway. It won't be too long until the property has more trees, bushes and shrubs than ever, but it will certainly look bare through the construction process.

VIEW FROM WATERWAY ROAD. PHOTO TAKEN 2-7-19

A MUDDY MESS, BUT ALL PART OF THE PROCESS. THESE EXCAVATOR OPERATORS ARE REAL PROS.


 

Come Worship With Us

Sunday Morning Worship

8:00 and 10:30

Sunday School at 9:30

 

Contact Us

Media Mennonite Church

866 Fifth Street

PO Box 70 

Oxford PA 19363

(610)932-9096

mediachurch@hotmail.com

 

Office Hours

8:00 - 1:00

Tuesday-Friday

 

We want to see everyone we know become more like Jesus.

Recommend this page on:

PrintPrint | Sitemap
© Media Mennonite Church